Good Progress Despite a Rainy Week

The only sun all week was this one
on our cabin wall, keeping me company
in the evenings.


The house is taking shape.
The previously built sundeck is in the foreground.


One more day of work is to be done before
the Christmas break. Then the house will
be covered with large tarps to protect it
from the rain.

The overall site view.
The re-located twenty year -old cabin is in the foreground

Some Framing Details

A still life of tools

View of roof rafters and loft joists

In the bedroom, looking out the desk bumpout

Framing detail in the living room

Framing detail on the west wall

Looking into the living / dining room from the kitchen

Framing the west wall

Framing detail in the living room

Looking out the bathroom window

Looking out the living room window bench
and double door leading to the veranda

The bathroom


Framing Progress - The Kitchen is Taking Shape

Just the kitchen floor so far

The view out the kitchen window

Walls going up

Paul and Shane working on kitchen framing

Windows and doors taking shape

Wednesday, December 10, 2014

A New High Point in Framing - the Roof Peak


A house is emerging.
Barry and Shane are high up in the rafters.
Barry is nailing in a rafter.

View from the sundeck.

Steve is helping Paul with the installation
of the drainage system.

Steve finished up for now.
Here he is standing on the parking
area, on top of "The Great Wall."

Friday, December 5, 2014

Framing Progress in the First Week of December

Framing of the main house has started
in spite of adverse weather.
(photo by Paul Hamson)

Framing of the south wall.
(photo by Paul Hamson)

View from the east.
The large opening will be the desk bumpout
protruding through the bedroom wall.

(photo by Paul Hamson)

Wednesday, December 3, 2014

Urs on Weekly Site Visit

The weather can be a challenge.
When I arrived it was -2C (30F) in the cabin, 0C (32F) outside.
Everything was frozen, including the water supply.
By 5pm, with the heater going, it was a balmy 15C (59F)
in the cabin; later a more comfy 20C. (68F)

A quiet evening at the cabin.
On the ferry going through Active Pass.

A first for me -
watching humpback whales in Active Pass.

Clear view to Mount Baker with Georgina Point
Lighthouse on Mayne Island in the foreground


Framed up to the Main Floor

Working at framing and subfloor.
The floor of Judy's kitchen.
View from east to west.
The sundeck is in the background.
Carport entry and access to crawl space.
Carport
View up the driveway.
The sundeck is in the foreground.
The whole main floor.
Important tool: Nail gun for framing nails.
Important tool: Chalk line

Important tool: Plumb line.